National Walking and Cycling Network - Project Progress
Project progress
In response to funding shortfalls it has been agreed to focus effort and prioritise routes, concentrating on those that have wide support and will deliver significant benefits.
Priority routes are highlighted in green.
Long Distance Routes - 5 year priorities requiring planning consent
Clyde Walkway extension - New Lanark to Biggar
- Status of route (new build/upgrade)
- Project development (feasibility studies, consultations) - Initial feasibility complete
- Design and construction - on hold
- Route launch and promotion - on hold
Project update
Initial feasibility study now complete. This included looking at links south to the Southern Upland Way, west to the River Ayr Way and east to the John Buchan Way. Further progress is on hold subject to funding. If funding is available the priorities are likely to be focussed on creating links between communities.
Progress updated March 2018
- Delayed or no further progress - subject to funding.
Crook of Devon to Kinross
- Status of route (new build/upgrade)
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - 2016/17/18
Project update
Route identified and build of Section 1 – Broomhill Cottage to Aldie lane, is currently underway. Building of further sections is planned for next fy – subject to funding.
- Update March 2017 - Broomhill Cottage to Aldie lane is now built. Good progress has been made on section 2 – Aldie lane to Balado station. Permissions are in place and funding secured for section 2 to be built towards the end of 2017.
- Update March 2018 - Consultation on route specifications have led to a delay with delivery of section 2. It is expected that this will be delivered during 2018.
Progress updated March 2018
- On track - design and build underway.
Cross-Scotland Pilgrim Way
- Status of route (new build/upgrade) - n/a
- Project development (feasibility studies, consultations) - n/a
- Design and construction - n/a
- Route launch and promotion - n/a
Project update
Discussions underway amongst partners on suitability of various surfaces in relation to their location and primary function.
- Update March 2017 - SNH funding currently diverted to other priorities.
- Update March 2018 - SNH funding still restricted.
Progress updated March 2018
- Delayed but recoverable - Good progress in some area.
a) Tyndrum to Glen Ogle
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - 2016/17/18/19
Project update
- Tyndrum to Crianlarich - Detailed feasibility study, community / landowner consultation, design and planning application is in progress. Estimated cost is £1M plus VAT. There is very little chance of raising this sum next fy so it is likely this section will be split into four separate projects focussing on community priorities.
- Update March 2017 - Phase 1 Tyndrum to Dalrigh under construction, nearing completion.
- Update March 2018 - Tyndrum to Dalrigh completed and opened. Further feasibility work being carried out on the Dalrigh to Crianlarich section.
- Crianlarich to Killin – initial feasibility study is complete. Further community / landowner consultation required.
Progress updated March 2018
- Delayed but recoverable - Good progress in some area.
b) Glen Ogle to Crieff
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - 2016/17/18
Project update
- NCN 7 link / Lochearnhead to St Fillans – Initial feasibility complete, but has raised various landowner issues. Further community / landowner consultation required in 16/17.
- St Fillans to Tynreoch – building of a Community Links path is underway due for completion by March 2016.
- Tynreoch to Crieff – Initial feasibility study / consultation has been undertaken. Further landowner negotiations are required.
- Update March 2017 - St Fillans – Tynreoch section now complete. Station Rd to Four Seasons hotel now under construction.
- Update March 2018 - Station Rd, St Fillans to Four Seasons hotel complete. Route now complete to Dalchonzie with land owner negotiation and design work being carried out for the Dalbeith section.
Landowner negotiations underway on the Tynreoch to Crieff section.
Progress updated March 2018
- Delayed but recoverable - Good progress in some area.
Darvel to Muirkirk
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - 2016/17/18
Project update
The route has been identified as having the potential to negatively affect designated sites. Further survey work is required during 16/17 to assess potential impacts and determine if the route is feasible.
- Update March 2017 - Route unlikely to progress due to funding constraints and concern over impacts on designated sites.
- Update March 2018 - No further work on this section.
Progress updated March 2018
- Delayed or no further progress - unlikely to progress.
John Muir Way – Strathblane to Glasgow spur
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Initial feasibility work is underway. The path has also been identified in the Strategic Development Plan for the area (Clydeplan). Work will be undertaken during 16/17 to gauge the extent of partner support.
- Update March 2017 - Initial feasibility complete. Landowner and Local Authority consultation underway with a view to work starting during 17/18
- Update March 2018 - Landowner and Local Authority consultation completed for first section of Allander Walkway as far as Balmuildy Bridge. TCV expected to start work on this section in April 2018.
Progress updated March 2018
- On track - ongoing - subject to feasibility study, partner support and funding.
North Solway Coast Path
North Solway Coast Path - Drummore to Portpatrick (South West Scotland Coastal Path)
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - tbc
- Route launch and promotion - 2019
Project update
Initial feasibility work is underway and early actions being identified. Further progress is expected during 16/17.
Update March 2017 - Improvements undertaken on various sections
Update March 2018 - Applications underway to Heritage Lottery Fund and Coastal Communities fund for £1.2M to improve 93km of path on the Rhins peninsular over the next two years.
Progress updated March 2018
- On track - ongoing.
Speyside Way extension – Aviemore to Newtonmore
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - complete
- Design and construction - ongoing
- Route launch and promotion - 2016/17
Project update
Aviemore to Kincraig was opened in September 2015. It is hoped to raise funds for the remainder of the route through to Newtonmore during 16/17.
- Update March 2017 - Specification for the Inshriach section is currently being worked on with planning permission and build hoped for this fy. Delivery of Inshriach to Ruthven is pencilled in for fy 18/19.
Both of the above sections will be reliant on timings of felling in the area.
- Update March 2018 - Funding secured to build the Inshriach section during 2018.
Progress updated March 2018
- On track - Building 16/17/18 subject to funding.
Other 5 year priorities
Arran Coastal Way improvements
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - complete
- Design and construction - complete
- Route launch and promotion - 2016
Project update
Complete – funding needed to repair storm damage.
- Update March 2017 - Works now completed to achieve SGT status.
Progress updated March 2018
- On track - complete.
Clyde Coastal Path
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - complete
- Design and construction - ongoing
- Route launch and promotion - complete
Project update
Complete – funding required for ongoing improvements / maintenance
- Update March 2018 - Improved signage installed early 2018.
Progress updated March 2018
- On track - ongoing improvements.
Clyde Walkway improvements: a) Newton Farm section
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding
- Update March 2017 - Lead partners have met with developers to discuss opportunities for improvements and links to the wider path network.
Progress updated March 2018
- Delayed but recoverable - subject to funding and agreements.
Clyde Walkway improvements: b) Craighead Retreat section
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding and planning
- Update March 2018 - Section from David Livingstone Centre to Craighead retreat upgraded to multi use.
Progress updated March 2018
- Delayed but recoverable - subject to funding and agreements.
Cowal Way improvements
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - complete
- Design and construction - complete
- Route launch and promotion - complete
Project update
- Improvement works complete.
Progress updated March 2018
- On track - complete.
Great Trossachs Path: Callander to Inversnaid
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - complete
- Design and construction - complete
- Route launch and promotion - complete
Project update
- Complete
Progress updated March 2018
- On track - complete.
Fife Pilgrim Way: Culross and North Queensferry to St Andrews
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - 2017
Project update
HLF bid successful during 2015 with a Project Development Officer being appointed to take things forward
- Update March 2017 - Further funding secured from HLF to fully develop the route
- Update March 2018 - Most planned path works now complete. Signposting and waymarking underway. Other elements being worked on include training opportunities, interpretation, web presence review.
Progress updated March 2018
On track - ongoing - successful HLF bid.
Hebridean Way - Harris & Lewis
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - complete
- Design and construction - complete
- Route launch and promotion - complete
Project update
- Complete
Progress updated March 2018
On track - complete.
John Muir Way - Kilpatricks section
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - complete
- Design and construction - complete
- Route launch and promotion - complete
Project update
- Complete – opened in March 2016
Progress updated March 2018
On track - complete.
Long term priorities
Aberdeenshire Coastal Path
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Angus Coastal Path
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Cross-Scotland Pilgrim Way - c) Iona to Tyndrum
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding
Update March 2017 - Lead partners working on proposal for Project Officer to take forward stage 2 of the consultation process during 17/18.
- Update March 2018 - No further action – subject to funding but likely to go ahead during 2018.
Progress updated March 2018
Delayed but recoverable - subject to funding.
Cross-Scotland Pilgrim Way - d) Crieff to St Andrews
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - Ongoing
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Crieff to Muthill – split into three stages. Stage one being built by March 2016. Further feasibility and fundraising required for stage s 2 & 3.
Muthill to St Andrews – various options exist depending on use and surface requirements - feasibility work is underway to identify the preferred option.
- Update March 2017 - Feasibility and route finding undertaken during 16/17. Further work expected during 17/18.
- Update March 2018 - Ongoing feasibility work for the River Earn crossing between Crieff and Muthill and for the wider Muthill to Perth area.
Progress updated March 2018
Delayed but deliverable - Ongoing - Three Saints Way.
Deeside Way extension
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - Ongoing
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding
- Update March 2017 - Further feasibility / landowner engagement is underway with a report due in May followed up by a planning application and possible build.
- Update March 2018 - Talks underway between SNH and CNPA to appoint a Strategic Routes Officer to help with delivery.
Progress updated March 2018
Delayed but recoverable - Ongoing subject to funding.
Glenbuck - New Lanark link
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility completed in 2015 as part of the Clyde Walkway Extension project. Now on hold subject to funding.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Inverness-Nairn Coast Path
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - 2016
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibiltiy study to be undertaken in 2016/17
Update March 2017 - Feasibilty unable to be progressed during 16/17 due to staff shortages. Work planned for 17/18 if staff resources and funding allow.
March 2018 update - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Kirkmichael - Ballater link
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding and feasibility.
Progress updated March 2018
Delayed or no further progress - Subject to funding and feasibility.
North Solway Coastal Path (South West Scotland Coastal Path)
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - Ongoing
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study is identifying early works
Update March 2017 - Lady Bay and Corsewall section - Drainage, surfacing, signage and access improvements including installation of self-closing gates, bridge and way marking at Lady Bay north of Kirkcolm.
March 2018 update - Now included as part of the wider South West Scotland Coastal Path project.
Progress updated March 2018
On track - Identifying and implementing early works.
Pitlochry - Kirkmichael link
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding and feasibility.
Progress updated March 2018
Delayed or no further progress - subject to funding and feasibility.
Stirling to Drymen
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
On hold subject to funding and feasibility.
Progress updated March 2018
Delayed or no further progress - subject to funding and feasibility.
Cycleways - 5 year priorities requiring planning consent
Route 73 of the National Cycle Network - Brodick to Corrie
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Route 753 of the National Cycle Network - Gourock-Ardrossan: a) Largs to Inverkip
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Route 753 of the National Cycle Network - Gourock-Ardrossan: b) In & around Fairlie
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
*Route 76 of the National Cycle Network - Manor Powis Roundabout
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Route 765 of the National Cycle Network - Stirling to Callander: Doune-Burn of Cambus
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Southern Upland Cycleway: Stranraer to Portpatrick
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Feasibility study for Inverness to Nairn planned for 16/17
- Update March 2017 - Unable to proceed during 16/17 and further uncertainty due to staffing levels.
- Update March 2018 - No further action.
Progress updated March 2018
Delayed or no further progress - subject to funding.
Other 5 year priorities
Route 73 (South) of the National Cycle Network
Newton Stewart to Cairnryan
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - Reliant on TS road schemes
- Design and construction - Reliant on TS road schemes
- Route launch and promotion - Reliant on TS road schemes
Project update
Route to Stranraer is now broadly complete but not yet signed. Sustrans to prepare and implement signage schedule. Remainder of scheme between Stranraer and Cairnryan still dependent on TS road schemes.
Update March 2017
No further progress to date. Sustrans to assess and consider options during 17/18.
Update March 2018
Signage has been put in place, but needs checks as some gaps in the signage have been highlighted.
Initial works to assess requirements between Stranraer and Cairnryan required..
Progress updated March 2018
Delayed or no further progress - Reliant on TS road schemes.
Dundee Green Circular – alternative to Docks
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Project cancelled.
Longer term priorities
Route 74 of the National Cycle Network: Gretna-Glasgow:
Project development (feasibility studies, consultations) - 2015/16 - ongoing
Route 74 of the National Cycle Network: Gretna-Glasgow:
a) Larkhall to Stonehouse
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
The route in this section is complete and operational. A signage audit will be carried out by Sustrans during 16/17.
Update March 2017
A signage audit is being carried out by Sustrans due to be completed mid 2017.
Update March 2018
On track - ongoing.
Route 74 of the National Cycle Network: Gretna-Glasgow:
b) M74 cycleway north end
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
The section of route between Lesmahagow and Happendon is currently under construction and is due for completion by May 2016. The missing section at Blackwood should be completed during 16/17. Update March 2017
Route complete and open
The section of route between Lesmahagow and Happendon is now complete and operational. A signage audit is being carried out by Sustrans due to be completed mid 2017. Update March 2018
On track - ongoing.
Route 74 of the National Cycle Network: Gretna-Glasgow:
c) To Douglas
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - tbc
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
The section from Happendon to the existing on road section at Douglas already exists and is operational. A full signage audit of the route from Gretna to Uddingston will be carried out by Sustrans during 16/17 and NCN 74 should essentially be complete. Update March 2017
The section from Happendon to the existing on road section at Douglas already exists and is operational. A signage audit is being carried out by Sustrans due to be completed mid 2017. Update March 2018
Route complete and open.
On track - ongoing.
Route 765 of the National Cycle Network
Stirling to Callander. Burn of Cambus to Callander
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - tbc
- Route launch and promotion - tbc
Project update
Initial route feasibility study, focusing on disused railway line, to be carried out by Sustrans engineering team during 16/17
Update March 2017
Proposed to be carried out either 17/18 or 18/19.
Update March 2018
SG funding confirmed for outline feasibility study to be carried out 18/19. Works to be lead by Sustrans and supported by LLTNPA. Landowner negotiations underway.
Delayed or no further progress - Subject to funding and resources.
Route 775 of the National Cycle Network
Almondbank to Lochearnhead: Crieff-Lochearnhead
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - tbc
Project update
Design works on Crieff sections underway. Some construction work at St Fillans also underway. Further discussions required with all stakeholders to agree lead partner and provide focus for delivery.
Update March 2017
Further discussions and support for Perth and Kinross Council around Crieff to Comrie section. Delays due to landowner issues.
Update March 2018
Additional sections have been added between St Fillans and Comrie and development of future phases underway.
Delayed but recoverable - Feasibility ongoing.
Route 79 of the National Cycle Network
Speyside Way Cycleway
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - tbc
Project update
Appraisal and options study for Speyside Way carried out by COAT during 15/16 FY. All partners (Moray Council, CNPA, The Highland Council and Sustrans) to meet during 16/17 and agree phased implementation of improvements and realignments.
Update March 2017
Initial improvements to Grantown on Spey to Nethy Bridge section being undertaken by CNPA/COAT during 2016/17
Update March 2018
No further works on this section last year.
On track - Feasibility / costing underway.
Fort William to Mallaig
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - Reliant on TS road schemes – discussion ongoing
- Design and construction - Reliant on TS road schemes
- Route launch and promotion - Reliant on TS road schemes
Project update
Meeting held with community and tourism representatives to explore some options. Definite demand for route but only very few expensive possible options. Considerable impact on trunk road so agreement and involvement of Transport Scotland required.
Update March 2017
Proposed STAG analysis of key routes to be led on by Sustrans and HiTrans during 17/18
Update March 2018
No progress on this last year. Initial route option appraisal to commence during 19/20.
Delayed or no further proress - Reliant on TS road schemes.
Roslin to Peebles Cycleway
- Status of route (new build/upgrade) - new
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - tbc
Project update
Sustrans working to support Scottish Borders Council to secure a route corridor between Peebles and Eddleston. Some land acquired through purchase, the remainder secured on a range of agreements. Initial design work completed and outline planning application to be submitted during February 2016.
Update March 2017
Approx 90% of required land corridor secured currently. Detailed design and planning currently being led on by SBC, funding from Sustrans
Update March 2018
Detailed design work, lead by Sustrans to commence during 2019 with cinstruction proposed for 2020.
On track - Route corridor investigation and planning ongoing.
CANALS - Other 5 year priorities
Caledonian Canal Towpath
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - ongoing
Project update
Dochgarroch East Towpath – 237m towpath upgrade
Banavie Lock Flight North – 3500m towpath upgrade
Banavie to Corpach – 3600m – towpath upgrade
Update March 2017
Inverness City – 295m - access improvements and towpath upgrades
Update March 2018
Muirtown Access Study
Upgrade of Caledonian Canal north towpath from Burnfoot Cottage to Kinmylies Slipway, Inverness
Upgrade of Laggan Swing Bridge access track at NCN 78 crossing of the A82
replacement of towpath gates along the Caledonian Canal with lockable lay-down bollards.
On track - ongoing.
Crinan Canal Towpath
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - ongoing
Project update
Crinan Bridge - 906m towpath upgrade
Oakfield to Cairnbaan - 3842m towpath upgrade
Update March 2017
Dunardry to Bellanoch bridge - 1860m – towpath upgrade
Bellanoch bridge to Crinan Ferry Bridge – 2170m – towpath upgrade
Ardrishaig basin to Oakfield bridge – 2653m – towpath upgrade
On track - ongoing.
Forth & Clyde Canal Towpath – including Port Dundas / Pinkston link
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - ongoing
Project update
Balmuildy Road - 1000m towpath upgrade
Auchindavie to Twechar – 3080 towpath upgrade
Bowling - 4500m towpath surfacing
Knightswood - 3100m - towpath LED Solar lights
Twechar to Auchinstarry - 3060m towpath upgrade
Stockingfield Junction - 150m towpath upgrade
Castlecary - 2371m towpath upgrade
Helix, Glensburgh - 400m towpath LED Solar lights
Ladiesmill - 300m towpath surfacing
Falkirk wheel corridor - 1100m towpath LED Solar lights
Carmuirs - 150m towpath upgrade
Bairds Brae, Glasgow - 180m Towpath link path upgrade
Update March 2017
Towpath upgrades at
• Hungryside – 86m
• Cadder – 114m
• Bonnybridge to Underwood lock 17 – 2215m
• Auchinstarry to Wynford lock 20 – 6090m
• Glasgow branch towpath – 330m
Update March 2018
Path construction & towpath upgrade
• Possil Greenspace – 1000m
• Spiers Wharf to Applecross – 700m
• Bowling Harbour Highline development – 500m
• Garscube bridge and connectivity study
• Stockingfield bridge feasibility and design
• Charlotte Dundas Heritage Trail (Signage and interp)
• Falkirk Cutting Rock removal
• Falkirk Wheel to Helix (Selfie with a Kelpie trail) - Signage, interpretation, seating & art installations
On track - Ongoing.
Monklands Canal Towpath
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - ongoing
Project update
Ongoing improvements.
On track - Ongoing.
Union Canal Towpath
- Status of route (new build/upgrade) - upgrade
- Project development (feasibility studies, consultations) - ongoing
- Design and construction - ongoing
- Route launch and promotion - ongoing
Project update
Winchburgh to Broxburn - 2982m towpath upgrade
Falkirk to Brightons - 4364m towpath upgrade
Ratho to Hermiston - 3105m towpath upgrade
Linlithgow - 1000m towpath LED Solar lights
Boroughmuir - 300m towpath upgrade
Update March 2017
Towpath upgrades at
• Edinburgh Lochrin – 120m
• Broxburn to Bonnington – 4988m
• Brightons to Linlithgow - 6313m
• Linlithgow to Winchburgh – 8542m
Update March 2018
Unlocking the Story Signage & interpretation Upgrade to Union Canal
22 km of solar lighting installed
On track - Ongoing.